The Cement Silo Work Process of HZS Concrete Batching Plant:

1, when the cement silo of hzs concrete batching plant work, it must be performed by a dedicated crane to erect, and then put on the basis of pre-prepared concrete and cement silo erected after checking the vertical and the horizontal level, and then at the bottom of the base pre-buried welding firm.

2, Storage silos fixed later by the bulk cement truck transporting cement to the site, and then the bulk cement truck delivery pipe and cement silo feed pipeline phase, through bulk cement truck’s gas tank pressure to deliver the cement into the cement silo.

3, In the process of transporting cement storage silos to the inside, the operator must press the dust vibration motor uninterrupted button attached to shake off the dust bag of cement to prevent blocked bags and warehouse explosion occurred.

4, Once blocked the bag, the pressure inside the cabin pressure exceeds the warehouse roof safety pressure relief valve, the pressure relief valve will open positions within the release pressure and prevent warehouse explosion accident.

5, By the level of material position, the hzs concrete batching plant can be observed in full and the lack of material warehouse.

6, When the hzs concrete batching plant is discharging, first open the manual discharge valve at the bottom of the cone, and then through the cement delivery device to transfer out of cement. In the discharge process, if there is “bagging” phenomenon, press the button on the arch breaker solenoid valves timely, eliminating the “bagging” in feeding, to ensure smooth supply of cement.

7, When the cement delivery device of hzs concrete batching plant fails, first turn off the manual discharge valve at the bottom of the cone to prevent cement spills, resulting in waste.